Project Owner Upper Occoquan Service Authority |
Contract Value $1,677,000.00 |
Architect/Engineer CDM Smith |
Project Location Centreville, Virginia |
Project Duration 2/24/2020-6/17/2021 |
Discipline Civil, Mechanical, Electrical |
UOSA ARRP Demolition
- Home /
- UOSA ARRP Demolition

Project Description
The project includes demolition and sitework at the Millard H. Robbins Jr. Regional Water Reclamation Plant (RWRP) at 14631 Compton Road, Centreville, Virginia 20121-2506. The Work includes structural and selective demolition of the Ammonia Removal and Recovery System (ARRP) facilities including Building M and Load Center No. 7, and associated sitework. The Work includes removal of existing facilities, infrastructure, and materials while other portions of the facilities remain in continuous service.