Project Owner WMATA Washington Metropolitan Area Transit Authority |
Contract Value $3,745,906.00 |
Architect/Engineer Gannett /Fleming /Parsons |
Project Location Greenbelt, MD |
Project Duration 04/19 – 11/19 (Project Completed December 9, 2019) |
Discipline Civil, Concrete & Paving |
Rehab Greenbelt Metro Parking Lot
- Home /
- Rehab Greenbelt Metro Parking Lot

Project Description
This construction project was for rehabilitation of the Greenbelt station parking lot, the work included but not limited to milling, asphalt paving, paving marking and striping, curb & gutter, sidewalk concrete, full depth pavement repair, maintenance & traffic, grading and signage.
This task order was performed in approximately 13 phases, moving approx. 400 parking spaces at a time to work in a given phase. The project had an approx. area of 1,400,000 Sq. Ft. Total, and was completed December 9, 2019.