Project Owner Washington Suburban Sanitary Commission |
Contract Value $6,588,000.00 |
Architect/Engineer O’Brian & Gere |
Project Location Potomac WFP, Potomac, MD 20854 |
Project Duration 10/1/2019 to 9/29/2020 |
Discipline Demolition, Architectural, Mechanical, Electrical and Plumbing |
Potomac WFP Filter Air Scour Upgrades
- Home /
- Potomac WFP Filter Air Scour Upgrades
Project Description
Construction of a new blower building encompassing precast building, concrete foundation & slab, new electrical services, blowers and stainless steel piping. Demolition and renovation of the existing filter air scour system in phases. Installation of site landscaping and sediment control systems. Integration of mechanical and HVAC controls into SCADA and BACnet systems.